SCOTIA-GLENVILLE
Vote set for $27M school bond
BY MICHAEL GOOT Gazette Reporter
Reach Gazette reporter Michael Goot at 395-3105 or mgoot@dailygazette.net.
A $27 million proposal to renovate district buildings and athletic fields
will head before voters on Dec. 16.
The Scotia-Glenville Board of Education on Monday formally voted to set
a referendum for a proposition to renovate classrooms at the middle and
high school, expand the high school library, construct a new athletic
field with artificial turf and make roof repairs and communications network
upgrades at the schools.
Board member Ben Conlon criticized what he said was misleading information
about the proposed project put out by the district and local media. The
board last week agreed to seek voter authorization for the general parameters
of the project — including choosing the second of two options that
had been discussed — expanding the existing library instead of constructing
a new library addition.
However, Conlon said, he believes the public assumed the project was approved
and therefore, there was no need for anyone to come out to Monday’s
meeting where the board formally voted on setting the referendum date.
“Our own Web site as of [Monday] said it was voted and approved
last week,” he said.
Board President Margaret Smith said it was unfortunate the information
on the district’s Web site was not clear about what the board did
last week, but Monday’s meeting was properly advertised.
“Clearly, the majority of the board understood that we were not
voting on the project,” she said.
Another concern of Conlon’s was the true cost of the project. District
officials have said that the bond payment would increase the tax rate
about 1.9 percent annually. This equates about $48 for a home with an
assessment of $150,000, $38 with the STAR rebate and $32 with the enhanced
STAR program. The gross cost of the project is $37.6 million when the
interest on the debt payments is included.
However, this figure takes into account money the district has in a reserve
account it is using toward the cost. Business Manager Andrew Giaquinto
said the tax impact would be 2.6 percent if that money were not factored
into consideration.
Conlon also expressed concern about the weak economy. “There’s
real possibilities of cutbacks in state aid,” he said.
The vote was 6-1 in favor of proceeding, with Conlon voting in opposition.
The proposal includes $5 million worth of general maintenance and roof
repairs at various buildings.
Another part of the project is renovating science and industrial technology
classrooms at the middle school and renovating technology classrooms at
the high school; enclosing the middle school library; and replacing the
football field with artificial turf, 500-seat bleachers and fixing the
track.
The district plans to hold community meetings to give residents more information
about the proposal on Nov. 12 and Nov. 15 and hold a public hearing tentatively
set for Dec. 8. Times and locations for the meetings will be announced.
|