Review of Glen-Worden tour:
v PA system a safety concern unable to hear in certain
areas.
v Library roof ice falling on sidewalk, barrels used in
past not completely effective, possibly extend roof canopy.
v Lighting concerns in Library if roof extended.
v Playing field generally a dustbowl, topsoil removed
when septic field was installed never replaced.
v Paving of parking lot Ðcompletion of paving from last
project and entrance to cafeteria.
v Other areas mentioned similar to other elementary
building
o Dirt floor in basement not conducive to storage or
practical usage.
o Windows
o Fire alarm system
v Changing rooms for both girls and boys.
Jim Rodecker mentioned that
a firm has been hired to evaluate the existing pa systems in all buildings
pertaining to replacement of removed speakers and any new additions for
workability.
Tour of Lincoln School:
¯ Library double doors not installed on last project
due to abatement missed.
¯ ÒLake LincolnÓ drainage in main entranceway.
¯ Bus loop in main entranceway to help with drop-off
and pick-up congestion.
¯ Cracking of exterior wall of gym.
¯ Asbestos floor tile in cafeteria and other areas of
building removed.
¯ Electrical upgrades with standby power building used
as evacuation site for 3 nursing homes.
¯ Issues similar to other buildings
o Carpeting over asbestos tiles removal with abatement.
o Carpeting also health issue Ðallergies.
o Bathroom renovation.